Conservation and Improvement Project - Week Ending 01st April 2016

This week has predominantly focussed on constructing the stage and repairing the internal plaster work where necessary.

The gallery of the stage is being boarded by reusing the flooring that was removed from the old Hall floor. We can now get the full impression of the stage and the timbers of the ceiling.

Cracks in the corners of the south wall need to be pinned and loose plaster has been removed and re-plastering has started. Where the walls have been channelled to take electricity cabling, these have now been filled. As with lime plaster the layers have to be built up slowly.

The Parish Hall Committee met this week and agreed the colour for the panelling.

The weekly project monitoring meeting was held on Thursday with Richard Boxall, Richard Slee and Steve Baber.