Friday 22 April 2016

Conservation and Improvement Project - Week Ending 22nd April 2016

This week Richard Frost, our Master Thatcher, has reached the ridge. The plasterwork around the new glazed door frame has been completed. The walls have been decorated in lime-wash with a parchment tone. The electrician has been on site and has started to fit the electrical sockets and light switches, and the down-lighters over the stage have been installed. The wall panelling has been painted and is near completion. On Monday we held our Project Finance Team meeting to review our expenditure and budgets. We remain on target to complete within budget and will now need to apply to Heritage Lottery for the second instalment of their grant. On Thursday we held our weekly Project Team meeting to monitor progress and plan the next phase of work.