Kitchen Units
All the kitchen units have been installed and worktops fitted. Cupboard doors and drawers have been added to finally complete. The worktops have been cut and fitted and the edging strips applied. The backboards have been fitted to the walls above the worktops.
Serving Hatch
The serving hatch has been completed and an oak sill fitted.
Plumber
The plumber has connected the sink unit, connection for the dishwasher, water supply for water boiler and fitted drainage pipe work.
Electrical Work
The electrician has now connected all the circuits for the white goods, power sockets, lighting and emergency lighting. He has tested the circuits and provided a certificate.
Painting and Decorating
The painter and decorator has been at the Hall this week and completed the painting of the walls and timber items, including the serving hatch, external door, internal door, cupboard above the oil tank, architrave and skirting.
Flooring
As a final task the stone flag floor has received a final coat of sealant.
Thanks - Trades People and Volunteers
Our thanks go to all the trades people and volunteers who have worked on this project and enabled this phase to achieve its planned outcome.
Thanks - Funders
This project has been possible as a result of the Heritage Lottery Fund who supported the conservation work, Devon Community Foundation - Batsworthy Wind Farm Community Fund, and all the contribution made through our own fund-raising.