Friday 2 February 2018

Kitchen Refurbishment Project Week Five

This week has seen the project make significant steps forward towards completion.
Floor
The flooring flags have been laid and the joints have been pointed. The floor will be sealed as one of the last tasks of this project.
Guttering
The fascia boards have been painted black. The heritage black aluminium guttering has been delivered from Guttercrest and fitted by Steve.
Serving Hatch
Mark has constructed bi-fold doors for the Serving Hatch and fitted them. They have been prepared ready for painting.
Cupboard Over Oil Tank Cupboard
Mark as constructed some cupboard doors and hung these to form the cupboard above the oil tank. 
Kitchen Units
Work installing the kitchen units has progressed well this week. All floor and wall hanging cupboards have been fitted and work tops cut to size.
Electrical Work
The electrician has been on site fitting the power sockets, lights, appliance circuits, and emergency lights.
Cooker, Dishwasher and Wall Mounted Boiler
The cooker dishwasher and wall mounted boiler have been delivered this week and in the Hall ready to be installed.
Plaster
The new plaster has been prepared and primed ready for final coat decoration.
External Kitchen Door
The external kitchen door has been constructed and fitted by Haydons. This door is draught proof, can be locked and opened from the outside and has an emergency exit crash bar fitted on the inside.