Conservation and Improvement Project - Week Ending 22nd January 2016


Monday, and with scaffolding in place, Richard Slee's team was able to start work on the roof timbers. The first job is to add battens to the existing rafters to add sufficient depth for insulation to be added between the thatch and the plaster board ceiling. Work carried on with this task throughout the week. By Friday it was possible to start cleaning the old timbers.

On Thursday the insulation materials were delivered to the Hall in readiness to install in the roof.

A Project Team meeting involving Richard Boxall (Project Manager), Richard Slee (Main Contractor), Richard Boyles (DART Electrics and project electrician) and Steve Baber (Project Lead) was held on Friday to finalise the locations of electrical fittings and cable routes. This enable Richard to start work on first fixing electrical cabling.

Friday and Richard Frost was at the Hall starting work on the thatched roof.