Conservation and Improvement Project - Week Ending 08 January 2016

Monday morning and Richard Slee's team were back on site preparing the Hall for the asbestos removal contractor to start removing the old asbestos based ceiling. The specialist company removing the ceiling were Shield Environmental Services  They worked from Monday until Thursday removing the ceiling product and cleaning the Hall. During the work access to the Hall was prohibited. A large container was delivered and left in the car park. This was used to dispose of the asbestos material.
On Friday it was possible to go into the Hall and see the roof timbers which are now exposed.
On Friday there was  site meeting of Richard Boxall (Project Manager), Richard Slee (Main Contractor), Richard Frost (Master Thatcher) and Steve Baber (Project Lead). The meeting was to plan the next stage of the works. Richard Slee and his team will be working inside the Hall continuing with the conservation work. Richard Frost will be starting to re-thatch the roof. The first task is to erect scaffolding both inside and outside the Hall and this should start next week.


 








No comments:

Post a Comment