Conservation and Improvement Project - Contractors On-site Week 4

Week beginning Monday 9th November
Richard Slee and his team and Bob Short the plumber, finished their work on the first phase of the project this week. They will return in January 2016 to continue the work.

Monday 9th 
Bob Short completed laying the underfloor heating pipe work, installed the manifold and pressure tested the systems. All OK.

Richard Slee's team started to screed the floor to cover the pipe work. The screed work is being done in two parts. Today the south end of the Hall was completed.

Tuesday 10th
Richard Slee's team continued to screed the floor and completed the north end of the Hall. The screed now needs some time to thoroughly dry before any more work can be carried out.

Wednesday 11th
Richard Slee's team on site and made an excellent job of tidying the Hall and the site generally as their conclusion to this first phase of work. Thanks go to the team.

Thursday12th
Parish Hall Trustees held there bi-monthly meeting and received a report on the progress of the work. Trustees are happy with progress to-date. They made a decision which allows the the conservation work to continue in January 2016, one month ahead of the original plan.

Friday 13th
Richard Boxall, Project Manager, and Steve Baber, Project Lead, met to review the work and plan for the next part of the project. One of the challenges is to locate the oil storage tank using the outside store. Some work will need to be undertaken in the kitchen to extend the store and make it fire-proof.