Week beginning Monday 26th October
Good progress has been made this week with observable results.
Monday 26th - Final preparation for concrete by installing the reinforcement mesh. Paul Waring ( Building Control Inspector) visited the Hall, approved the works to-date and agreed that the concrete sub-floor could be laid. Richard Boxall (Project Manager) Steve Baber (Project Lead) and Richard Slee (Contractor) held a progress meeting and confirmed quality and pace were in line with our requirements.
Tuesday 27th - 9.00am and the concrete mixer arrived. The concrete had to be barrowed from the mixer to the inside of the Hall. Richard Slee and his team work all morning laying the concrete sub-floor.
Wednesday 28th - The main job today was to lay the floor foundation that will be under the stage. The concrete was mixed by hand using a portable concrete mixer.
Thursday 29th - The form to support the concrete retaining walls under the stage was constructed. Laying the insulation on top of the concrete sub-floor in the hall was started.
Friday 30th - The retaining walls under the stage were concreted. The weekend allows time for the concrete to 'go off' before work starts again next week.