Steve Baber and Ron Moore worked to break through to the trench under the wall in the storeroom to enable the power supply cable to be routed into the storeroom. The floorboard in the Hall where the existing power supply is located under the floor have been lifted to allow Western Power access to withdraw the cable and re-route it.
Tuesday, 29 September 2015
Monday, 28 September 2015
Re-routing Electrical Supply
Western Power on site and have dug the trench external to the Hall wall to re-route the electrical supply cable from under the floor in the Hall to its new location in the storeroom.
Lime Plastering Wall in Storeroom Continues
Saturday, 19 September 2015
Under the Storeroom Floor
Tuesday, 15 September 2015
Asbestos Survey
Before conservation work can start on the Hall an intrusive asbestos survey has to be carried out. Today AMS 2000 Ltd from Barnstaple carried out the survey. We await their report.
Friday, 11 September 2015
Lime Plastering Wall in Storeroom
Friday 11th September Richard Boxall continues to plaster the wall in the storeroom. Lime plaster requires several layers building up slowly with each layer drying before the next layer is applied. The wall need three layers
Thursday, 10 September 2015
EWPH - Heritage Group Meeting August 2015
Our August minutes are now on line. We held our monthly meeting on Monday - so much local history to find out about and look at, really interesting.
Saturday, 5 September 2015
Work Starts Preparing Storeroom Wall
Saturday 5th September Richard Boxall and Steve Baber started working on the wall in the storeroom. This work is needed to prepare the wall in readiness for the new location of the rerouted power supply, electric meter and consumer unit. The wall need plastering with lime plaster.