Tuesday, 10 May 2016
EWPH – Heritage Group Meeting - April 2016
The minutes of our Group's last meeting in April are on line should you wish to see how we're getting on.
Friday, 6 May 2016
Conservation and Improvement Project - Week Ending 6th May 2016
This week the oak glazed doors have been sealed with a thin protective sealant. The joiner has been working in the Hall to finish the stage detail and create the under-stage storage area. Richard Frost our Master Thatcher has finished the thatching of roof.
Friday, 29 April 2016
Conservation and Improvement Project - Week Ending 29th April 2016
This week the electrician has been on site adding example lighting to the Hall so that its possible to make a choice about the lighting solution. The plumber finished off adding the radiators in the toilets and also connected the hot water supply to the sinks. Graham Haydon's team were on site and hung the large oak doors that will be glazed. The Parish Hall Committee met at the Hall on Friday evening to decide on the lighting solution and to agree the direction of the wooden flooring that is planned to be installed within two weeks.
Friday, 22 April 2016
Conservation and Improvement Project - Week Ending 22nd April 2016
This week Richard Frost, our Master Thatcher, has reached the ridge. The plasterwork around the new glazed door frame has been completed. The walls have been decorated in lime-wash with a parchment tone. The electrician has been on site and has started to fit the electrical sockets and light switches, and the down-lighters over the stage have been installed. The wall panelling has been painted and is near completion. On Monday we held our Project Finance Team meeting to review our expenditure and budgets. We remain on target to complete within budget and will now need to apply to Heritage Lottery for the second instalment of their grant. On Thursday we held our weekly Project Team meeting to monitor progress and plan the next phase of work.
Friday, 15 April 2016
Conservation and Improvement Project - Week Ending 15th April 2016
This week progress with the thatching continues as the thatcher reaches the top of the roof. Inside work has been undertaken to prepare for fixing of the light fittings. The walls of the Hall are being decorated using lime wash in a parchment tone. Graham Haydon's team have been on site and fitted the oak door frame that will support the glazed door in front of the old barn door. They also fitted the rails on the stage gallery.
Tuesday, 12 April 2016
Heritage Minutes and past local information
Minutes of our February meeting now available on line.
Did you know that its believed most of the cottages in West Worlington were orignally Estate workers cottages?
Did you know that its believed most of the cottages in West Worlington were orignally Estate workers cottages?
Friday, 8 April 2016
Conservation and Improvement Project - Week Ending 08th April 2016
This week the focus is on inside repairs and preparation for decorating.
The cracks in the wall and the channels for cabling have been re-plastered. Rotten wood on the window has been removed and new timber spliced into the frame. The old barn door has had woodworm treatment. The ceiling above the stage has been plastered.
The cracks in the wall and the channels for cabling have been re-plastered. Rotten wood on the window has been removed and new timber spliced into the frame. The old barn door has had woodworm treatment. The ceiling above the stage has been plastered.